· SPYGLASS · PROGRAM CONTROL TOWER
PPM and Governance · WS8 Active · Phase 3 of 4 · Month 14 of 18
CPI 0.96 · ON BUDGET SPI 0.93 · 2 WK SLIP 1 RED RISK OPEN
14:22 ET MAY 1, 2026
PHASE 0
Discovery
Closed · SG1 ✓
PHASE 1
Foundation
Closed · SG2 ✓
PHASE 2
Activate
Closed · SG3 ✓
PHASE 3
Optimize
In flight · 67% complete
PHASE 4
Sustain
Starts Jul 2026
CPI
0.96
+0.02 wk
Target ≥ 0.95
SPI
0.93
-0.01 wk
Target ≥ 0.95
EAC
$3.74M
+$40K vs BAC
BAC $3.60M (capped)
VAC
-$140K
3.9% over
Within 5% tolerance
Sprint Velocity
38pts
-6 vs trailing avg
Target 44 pts
OTIF MTD
93.4%
+0.6 pts
Target 95.0%

Workstream Health

Phase 3 status by workstream SMARTSHEET
WSWorkstreamPhase % DoneCPISPIRAG
WS0Program FoundationClosed100%1.021.00G
WS1Inventory Sync AgentPhase 388%0.970.96G
WS2Master Data & Production LogicPhase 381%0.940.92A
WS3Reporting LibraryPhase 376%0.990.95G
WS4Demand & Supply PlanningPhase 362%0.910.86R
WS5Financial Close AutomationPhase 370%0.960.93A
WS6Spyglass Production DashboardsPhase 355%0.970.94A
WS7Redwood MigrationStabilize94%1.010.98G
WS8AI Governance & Training CURRENTPhase 348%0.950.92A

Cost Curve

PV vs EV vs AC cumulative SMARTSHEET

Top Risks Now

RAID excerpt · sorted by exposure SMARTSHEET
R-014   WS4 hypertuning blocked by demand history depth
3 item families fall below the 18 month minimum. Mitigation: temporary classical baseline. Owner: Pedro AG. Due: 2026-05-08.
R-021   WS6 dashboard activation contingent on WS7 stabilization
Redwood stabilization not yet at 90 day mark. Conditional go-live targeted for 2026-06-15. Owner: Chris Clark.
R-017   WS8 adoption metric coverage incomplete
Persona based adoption baseline missing for Plant Floor and Finance Close. Champion network expansion in progress. Owner: Brianna.
R-019   Vendor SOW V3 amendment not yet signed
SI T&M to fixed fee conversion for Phase 3 awaiting CFO signature. Owner: Tom Chartrand.
R-022   Agent token spend trending +18% vs forecast
WS1 production agents exceeding modeled token budget. Triage: prompt compression and caching review. Owner: Sasi.

Inventory Accuracy
98.2%
+1.8 pts vs baseline
Target 99.0%
Forecast MAPE
14.6%
-2.4 pts vs baseline
Target ≤ 13.5%
Expedite Spend YTD
$614K
-$210K vs prior YTD
Run rate $0.95M ann.
Close Cycle Days
5.2
-1.4 days vs baseline
Target 4.0 days
BAC
$3.60M
Capped (BAFO capped baseline)
EAC
$3.74M
+$140K vs BAC
AC to date
$2.51M
70% of BAC
ETC
$1.23M
Remaining work
Contingency
$220K
61% remaining
KPI Incentive Pool
$210K
$135K earned to date

Spend by Workstream

Actual vs plan, in flight workstreams SMARTSHEET

Spend by Phase

Cumulative spend vs phase budget SMARTSHEET

Vendor Spend & Burn

Active vendors by SOW SMARTSHEET
VendorTypeSOWInvoicedOpen POBurn %Status
Lead SI PartnerSI · T&M cap$3,600,000$2,184,000$418,00061%G
Planning Platform VendorSaaS · 3-yr$2,200,000$734,000$033%G
Planning Implementation (WS4)Fixed fee$1,800,000$1,134,000$222,00063%A
Niche AI Specialist (Phase A)Fixed$237,000$237,000$0100%G
Governance Advisory (WS8)T&M$370,000$182,000$049%G
Oracle (Agent Studio uplift)SaaS$140,000$98,000$070%G

Cost Type Mix

YTD AC composition SMARTSHEET
AI infrastructure (Oracle Agent Studio, OCI compute, model tokens) growing as Spyglass agents move to production. Token budget under active review (RAID R-022).
Story points planned
412
Phase 3 plan total
Story points done
274
66% complete
Velocity (3-spr avg)
38pts
-6 vs trailing
Target 44
Burn projection
+11d
vs Phase 3 baseline
Defect escape rate
2.1%
-0.4 pts
Target ≤ 3%
DoD compliance
96%
Target 95%

Phase 3 Burn-Down

Story points remaining by sprint JIRA

Cumulative Flow

Backlog · In progress · Done JIRA

Velocity by Workstream Squad

Last 6 sprints, story points completed JIRA
PV (BCWS)
$2.71M
Planned to date
EV (BCWP)
$2.52M
Earned to date
AC (ACWP)
$2.51M
Actual to date
SV
-$190K
Behind schedule
CV
+$10K
On budget
TCPI
1.04
to recover BAC

EVM by Workstream

PV / EV / AC and earned value indices SMARTSHEET
WSWorkstream PVEVAC CVSV CPISPI EACVAC
WS0Program Foundation $120K$120K$118K +$2K$0 1.021.00 $118K+$2K
WS1Inventory Sync Agent $420K$402K$415K -$13K-$18K 0.970.96 $478K-$8K
WS2Master Data & Prod. Logic $310K$285K$303K -$18K-$25K 0.940.92 $425K-$23K
WS3Reporting Library $240K$228K$230K -$2K-$12K 0.990.95 $298K-$3K
WS4Demand & Supply Planning $610K$524K$576K -$52K-$86K 0.910.86 $890K-$80K
WS5Financial Close Automation $215K$200K$208K -$8K-$15K 0.960.93 $240K-$5K
WS6Spyglass Production Dashboards $240K$232K$239K -$7K-$8K 0.970.94 $444K-$12K
WS7Redwood Migration $390K$394K$390K +$4K+$4K 1.010.98 $415K+$3K
WS8AI Governance & Training $165K$157K$165K -$8K-$8K 0.950.92 $346K-$14K
TOTProgram Total $2.71M$2.52M$2.51M +$10K-$190K 0.960.93 $3.74M-$140K

CPI Trend by Workstream

Last 8 weeks SMARTSHEET

SPI Trend by Workstream

Last 8 weeks SMARTSHEET
Sprints completed
22 / 36
Across program
Active sprints
6
All Phase 3
Carryover items
17
From sprint 21
PR cycle time (avg)
1.8d
Target ≤ 2.0d
UAT pass rate
91%
Target 90%
Spillover %
12%
Target ≤ 10%
PHASE 3 · OPTIMIZE
Mar 2026 to Jun 2026 · 12 sprints · 6 active
JIRA
SPR 22
WS1 · INV SYNC
Apr 21 to May 4 · Auto-recon precision uplift
34 / 44 pts 3 carry SPR 22 of 28
SPR 22
WS2 · MDM
Apr 21 to May 4 · Routing & work def cleanup
22 / 38 pts 5 carry SPR 22 of 28
SPR 22
WS4 · D&S PLAN
Apr 21 to May 4 · Hypertuning prereqs
18 / 44 pts 9 carry SPR 22 of 28
SPR 22
WS5 · FIN CLOSE
Apr 21 to May 4 · Inventory subledger recon
28 / 40 pts 2 carry SPR 22 of 28
SPR 12
WS6 · SPYGLASS
Apr 21 to May 4 · Control tower v0.4
26 / 40 pts 2 carry SPR 12 of 18
SPR 14
WS8 · GOV & TRAIN
Apr 21 to May 4 · Persona training & agent reg.
22 / 42 pts 4 carry SPR 14 of 22
PHASE 2 · ACTIVATE
Nov 2025 to Feb 2026 · 8 sprints · closed at SG3
SPR 14-21
WS1 · INV SYNC
Production readiness & agent rollout
312 pts doneDoD met
SPR 14-21
WS2 · MDM
Item attribution baseline
284 pts doneDoD met
SPR 14-21
WS3 · REPORTING
Library v1, governance defined
198 pts doneDoD met
SPR 14-21
WS7 · REDWOOD
UX migration & embedded AI feature catalog
356 pts doneDoD met
PHASE 1 · FOUNDATION
Jul 2025 to Oct 2025 · 8 sprints · closed at SG2
SPR 6-13
WS1 · INV SYNC
Auto-recon agent design & HITL workflow
248 pts doneDoD met
SPR 6-13
WS3 · REPORTING
KPI canonicalization & Excel deprecation
176 pts doneDoD met
SPR 6-13
WS4 · D&S PLAN
Demand signal audit, MAPE decomp
222 pts doneDoD met
SPR 6-13
WS7 · REDWOOD
Migration prep, environment strategy
164 pts doneDoD met
OTIF MTD
93.4%
+0.6 pts wk
Target 95.0%
Inventory Sync acc.
98.2%
+1.8 pts
Target 99.0%
Forecast MAPE
14.6%
-2.4 pts
Target ≤ 13.5%
Close Cycle
5.2d
-1.4 d
Target 4.0 d
Exception SLA
96.1%
+0.4 pts
Target 95.0%
Planner Touch
-42%
vs baseline
Target -50%

OTIF Trend

Daily, last 90 days ORACLE

KPI Progress vs Stage Gate Targets

Phase 3 incentive triggers ORACLE
OTIF (target 95%)
93.4%
Inventory accuracy (99%)
98.2%
MAPE (≤ 13.5%)
14.6%
Close cycle (≤ 4.0 d)
5.2 d
Exception SLA (95%)
96.1%
Planner touch reduction (-50%)
-42%

Outcome Achievement

11 outcomes from Byrne AI readiness assessment ORACLE
#OutcomeOwning WS BaselineCurrentTarget StatusIncentive
O1Inventory accuracy liftWS1, WS296.4%98.2%99.0%On track$30K earned
O2Forecast MAPE reductionWS417.0%14.6%13.5%RiskPending SG4
O3OTIF liftWS1, WS4, WS590.6%93.4%95.0%On track$45K earned
O4Expedite spend reductionWS1, WS4$1.05M$0.61M YTD-15% ann.On track$25K earned
O5Close cycle compressionWS56.6 d5.2 d4.0 dRiskPending SG4
O6Exception MTTR reductionWS642 hr28 hr25 hrOn track$15K earned
O7Planner touch reductionWS4100%58% (-42%)50% (-50%)On track$10K earned
O8Working capital releaseWS1, WS4$22.4M$21.0M-5% ($21.3M)Met$10K earned
O9Adoption (active users)WS838%71%85%RiskPending SG4
O10Agent governance complianceWS8n/a100%100%Met$0K (gate)
O11Data platform readinessWS262%88%95%On track$0K (gate)
Earned to date $135K of $210K incentive pool. Two outcomes (MAPE, Close Cycle) on amber pending Phase 3 closeout. Adoption (O9) is the WS8 priority for the next two sprints.

Program Health

Reported to SteerCo bi-weekly
LensStatusHeadline
ScopeG9 workstreams in flight, no scope additions
ScheduleASPI 0.93, Phase 3 forecast +11 days
CostGCPI 0.96, EAC $3.74M vs BAC $3.60M
QualityGDefect escape 2.1%, UAT pass 91%
RiskRR-014 WS4 hypertuning blocked, R-021 WS6 dependency
ResourceGFully staffed, SI T&M cap not yet breached
AdoptionA71% active, target 85% by SG4
GovernanceGAI Operating Model in compliance, agent registry current

Stage Gate Posture

Phase 3 close out criteria
SG4-1 · OTIF lift > 93%
MET
SG4-2 · MAPE ≤ 13.5%
RISK
SG4-3 · Inventory acc > 98%
MET
SG4-4 · Close cycle ≤ 4.5 d
RISK
SG4-5 · Adoption > 80%
RISK
SG4-6 · Agent governance compliant
MET

Decisions Required

For next SteerCo · May 8
D-007   Approve WS4 mitigation: classical baseline for 3 item families
Recommendation: approve. Allows WS4 to keep momentum while demand history depth catches up. Owner: Pedro AG. Resource: 2 sprints.
D-008   Endorse WS8 adoption playbook V2
Champion network expansion to Plant Floor and Finance Close. Adds $25K of WS8 effort, fully within contingency.
D-009   Sign SI SOW V3 amendment
Convert remaining T&M to fixed fee for Phase 3 closeout. Caps remaining exposure at $480K. Awaiting CFO signature.

RAID Log

Risks, Assumptions, Issues, Dependencies SMARTSHEET
Type
ID
Description
Owner
Severity
Likelihood
Status
RISK
R-014
WS4 hypertuning blocked by demand history depth (3 item families < 18 mo) Mitigation: classical baseline for 3 families, hypertune at SG5
Pedro AG
High
High
Mitigating
RISK
R-021
WS6 dashboard activation contingent on WS7 stabilization 90 day mark Conditional go-live targeted for 2026-06-15
Chris Clark
Med
High
Tracked
RISK
R-017
WS8 persona based adoption baseline incomplete for Plant Floor and Finance Close
Brianna
Med
Med
In flight
RISK
R-019
Vendor SOW V3 amendment unsigned. Remaining Phase 3 T&M exposure $480K CFO signature requested 2026-04-25
Tom Chartrand
Med
Low
Pending
RISK
R-022
WS1 agent token spend +18% vs forecast Triage: prompt compression, response caching
Sasi
Med
Med
In flight
ISSUE
I-008
UAT environment data refresh failed twice in past two weeks Root cause: OIC orchestration timeout. Permanent fix in PR-244
Sasi
Med
n/a
In progress
ISSUE
I-011
WS2 master data discrepancy between WMS and Fusion for 142 SKUs Reconciliation script run, manual review by SCM team underway
Pedro AG
Med
n/a
In progress
ASSUMP
A-005
Oracle 26B Agentic Apps GA targeted for May 2026 WS6 design assumes GA by go-live. Backup: custom build path
Chris Clark
Med
Low
Holding
ASSUMP
A-009
Champion network capacity sufficient for Phase 4 sustain mode
Brianna
Low
Low
Holding
DEP
D-003
WS6 Spyglass go-live depends on WS7 Redwood stabilization (90 day quiet period)
Chris Clark
Med
n/a
In flight
DEP
D-006
WS5 Financial Close depends on WS2 master data cleanup completion
Brianna
Low
n/a
On track
DEP
D-007
WS8 training content depends on Redwood feature catalog finalization (WS7)
Brianna
Low
n/a
On track

Weekly SteerCo Summaries

Bi-weekly cadence · chaired by Chris Clark
2026-04-24 · SteerCo #25
Chartrand · Wood · Amador-Gates · Brianna · Sasi · CClark

Headline

  • Phase 3 at 67% complete. CPI 0.96, SPI 0.93. Two amber stage gate criteria.

Decisions Made

  • Approved WS4 classical baseline mitigation for three item families (D-006).
  • Endorsed token budget review path for WS1 agents (R-022).
  • Deferred WS6 conditional go-live decision to next session pending WS7 stabilization read out.

New Risks Logged

  • R-022 WS1 agent token spend overrun (Med/Med).

Action Items Closed

  • 3 of 8 actions closed since SteerCo #24. See Actions tab for current backlog.
Full minutes (45 min session)
Chartrand opened with confirmation that the Spyglass program continues to track within the BAFO capped budget. CFO underwriting of the WS4 classical baseline mitigation was secured before the session. Wood reiterated the Phase 4 sustain mode commitment from Operations. Amador-Gates raised the master data discrepancy on 142 SKUs (I-011), with reconciliation script complete and manual review owned by SCM. Brianna walked through the persona based adoption gap for Plant Floor and Finance Close, with champion network expansion proposed as the path. Sasi presented the agent token spend trend with a triage path (prompt compression, response caching) targeted for closure within two sprints. Decisions D-007 (WS4 mitigation), D-008 (WS8 playbook V2) and D-009 (SI SOW V3) routed for next session.
2026-04-10 · SteerCo #24
Chartrand · Wood · Amador-Gates · Brianna · CClark · SI Lead

Headline

  • WS7 Redwood entered stabilization. Embedded AI feature activation tracking on plan.

Decisions Made

  • Approved WS6 design freeze and dependency tracking against WS7 stabilization.
  • Approved Phase 3 incentive payout schedule for outcomes O1, O3, O4, O6, O7, O8.
Full minutes (52 min session)
SI Lead briefed on capacity for the remainder of Phase 3. WS7 stabilization owners confirmed two consecutive clean weeks of incident free operation. Brianna reported persona based adoption baseline at 71% with a path to 85% by SG4. Chartrand asked for a hard cap on agent infrastructure spend separate from the SI budget. Action recorded for CClark to bring back a token cost forecast at the next session.
2026-03-27 · SteerCo #23
Chartrand · Wood · Amador-Gates · Brianna · Sasi · CClark

Headline

  • WS7 Redwood Phase 2 exit on plan. WS4 demand signal audit surfaced 3 deficient item families.

Decisions Made

  • Phase 2 closed at SG3 on time. SG3 retrospective scheduled.
  • WS4 mitigation triage routed to Pedro AG for proposal at SteerCo #24.
Full minutes (48 min session)
Chartrand commended the team on a clean SG3 close out. Wood stressed that WS4 deficiencies must not create a cascade into WS6 timing. Sasi briefed on OIC orchestration stability post Phase 2 cutover. The session ended with a unanimous SG3 sign off.

Actions Log

Cross-meeting tracker · current backlog 17 open / 9 closed past 30d SMARTSHEET
ID
Action
Owner
Source
Due
Status
A-101
Bring back agent token cost forecast and proposed cap to SteerCo #26
Chris Clark
SteerCo #24
2026-05-08
In progress
A-102
Run WS4 demand signal audit refresh against latest 6 weeks of data
Pedro AG
SteerCo #25
2026-05-15
In progress
A-103
Champion network expansion playbook for Plant Floor and Finance Close
Brianna
SteerCo #25
2026-05-22
In progress
A-104
SI SOW V3 amendment review and CFO signature
Tom Chartrand
SteerCo #25
2026-05-08
At risk
A-105
WS6 conditional go-live decision package for SteerCo #26
Chris Clark
SteerCo #25
2026-05-08
In progress
A-106
UAT environment refresh permanent fix (PR-244 merge and validate)
Sasi
SteerCo #25
2026-05-12
In progress
A-107
Master data reconciliation: 142 SKU manual review with SCM
Pedro AG
SteerCo #25
2026-05-09
In progress
A-108
Phase 4 sustain mode org design draft
Dan Wood
SteerCo #24
2026-05-22
In progress
A-109
Vendor handoff documentation for Phase 4 (SI exit plan)
SI Lead
SteerCo #24
2026-06-05
In progress
A-110
Refresh ROI model with realized outcomes O1, O3, O4, O6, O7, O8
Chris Clark
SteerCo #25
2026-05-15
In progress
A-097
WS7 stabilization 60 day report
Sasi
SteerCo #23
2026-04-22
Closed
A-095
Phase 3 incentive payout schedule for outcomes met
Brianna
SteerCo #23
2026-04-19
Closed
Modeled 3-yr value
$3.0-5.0M
Business case range
Realized YTD
$1.18M
vs $0.95M plan
Forecast 3-yr
$4.42M
Mid-band of model
Program cost
$3.74M
EAC
Net 3-yr value
$0.68M
Forecast - EAC
Payback
28mo
vs 36 mo plan

Realized vs Forecast Value

Cumulative quarterly · modeled bands shown

Value by Driver

Realized YTD plus forecast to year three
DriverRealized YTDYear 1 fcstYear 2 fcstYear 3 fcstTotal
Inventory reduction (working capital)$340K$520K$640K$680K$1.84M
Expedite avoidance$210K$340K$420K$450K$1.21M
Labor productivity (planning & finance)$280K$390K$470K$490K$1.35M
Exception cycle reduction$140K$220K$280K$300K$0.80M
Margin protection (service reliability)$210K$320K$410K$440K$1.17M
Total$1.18M$1.79M$2.22M$2.36M$6.37M
Cumulative 3-year forecast of $6.37M is above the modeled mid-band of $4.42M, driven by stronger than expected inventory reduction and expedite avoidance lift.

Outcome to Value Bridge

Each outcome mapped to a dollar lever and current realization
Outcome$ LeverRealized YTDYTD PlanVarianceConfidence
Inventory accuracy lift (O1)Working capital release$340K$280K+$60KHigh
OTIF lift (O3)Margin protection$210K$180K+$30KHigh
Expedite spend reduction (O4)Expedite avoidance$210K$160K+$50KHigh
Close cycle compression (O5)Labor productivity (Finance)$95K$110K-$15KMed
Exception MTTR (O6)Exception cycle reduction$140K$120K+$20KHigh
Planner touch reduction (O7)Labor productivity (Planning)$185K$200K-$15KMed